Back to projects
MISOMIS-2024-0103Under Construction

MI Solar Creek I

Located in MI. Developed by Apex Clean Energy. Interconnects via MI-SUB-103 on the ConEd system.

Capacity
635 MW
Technology
Solar
Expected COD
Q4 2029
Stage
IA Executed
Investability score44/100
44

Stage progression

MI Solar Creek I interconnection milestones

Source: Glass · ISO queue updates

LMP at POI

12-month average, MI-SUB-103

USD/MWh

Source: Glass · gridstatus / ISO LMP

Score breakdown

Six-factor investability assessment

Source: Glass · proprietary scoring model v1.2

Interconnection stage+21

IA executed and FFS complete — late stage signal.

Developer track record+14

Tier B developer with 14 completed projects.

Tax credit qualification+18

Energy community + domestic content bonuses available.

Permitting risk+8

County-level approval pending.

Grid context+6

POI has 120 MW of headroom; LMP averaging $38/MWh.

Market signals+3

Limited offtake competition in this corridor.

Recommended credit
ITC
Effective rate
50%
Estimated value
$317.5M
Estimated cost
$635.0M

Credit composition

ITC stack with IRA bonuses

%

Source: Glass · Treasury Notice 2026-15 model

Developer

Apex Clean EnergyView full developer profile
Profile
Queue IDMIS-2024-0103
ISOMISO
Queue date2022-04-15
IA statusIA Pending
POIMI-SUB-103
Transmission ownerConEd
Expected COD2029-10-01
StageIA Executed

Equipment & supply chain

FEOC overlay, supplier graph, and BOM analysis — Phase 4 enrichment.

Permitting

County-level approval status, filings, and timelines — Phase 4.

Capacity headroom at POI

MI-SUB-103

MW

Source: Glass · ISO transmission study data

Market context

Comparable projects, regional trends, and offtake market — Phase 2.